Eagle Mountain High School
The district’s fourth comprehensive high school has been named Eagle Mountain High School, and the District will begin the planning and design process in 2019.
Projected Opening: August 2024
Mascot: Knights
Colors: Black & Old Gold
August 24, 2024 Update
- Upper basketball gym striping is complete.
- Baseball turf infill is in progress. Turf to be completed by August 19.
July 22, 2024 Update
- The dry creek courtyard and stair entrances are complete.
- The library, logo, and main academic corridors are complete.
- Stadium press box logos have been installed.
June 17, 2024 Update
- Field house and track have been completed and student workouts began June 3.
- Kitchen serving line has been completed. Cafeteria stage platform is complete. High corridor pendent lights and sound panels have been installed.
- Large lecture hall wood and light fixtures have been installed. Small lecture hall is complete.
May 28, 2024 Update
- Tennis court and auxiliary field are complete.
- Progress continues on the dry creek courtyard.
- Small lecture hall wood paneling has been installed. Large lecture hall wood paneling and acoustic panels installation are in progress.
April 22, 2024 Update
- Hard ceiling, paint, and flooring have been installed in the field house locker rooms.
- Auditorium wood panel installation is nearing completion. Auditorium lobby ceiling installation is ongoing. Acoustical ceiling panels have been installed in band hall areas.
- Off-side road work on Fleming Ranch Rd. is ongoing and near completion.
- Landscaping continues around the campus
March 25, 2024 Update
- Softball field turf logo has been installed.
- Track asphalt and paving has been installed.
- Indoor practice turf installation is complete.
- Auditorium wood veneer panels is ongoing.
February 26, 2024 Update
- Stadium visitor’s side concourse paving installation. Storage building masonry ongoing.
- Field house weight room overhead ductwork and framing ongoing.
- Indoor practice facility turf field grading and poly liner installation in progress.
- Tennis court entrance paving formed in preparation to pour.
- Dry creek stone paver installation at pedestrian bridge.
- Gymnastics gym structure paint complete.
January 22, 2024 Update
- Patio poured and exterior storefront installed at the main entry. Metal panels and lighting install is in progress under the bridge. Interior stone at large lecture hall is complete.
- Lower ceiling in library has been framed and lighting installation is in progress.
- Library casework installation has started on main level.
- Cloud installation is complete. Auditorium finishes are ongoing.
- Installation of lockers in gymnasium continues.
December 11, 2023 Update
- Glazing, fascia metal, stone, and brick veneer has been installed in the auditorium entrance.
- Auditorium cloud ceiling is installed and scaffolding is being dismantled.
- Large lecture hall interior stone veneer is in progress.
- Skybridge sheathed in preparation for soffit panels.
November 17, 2023 Update
- The upper level classroom windows are complete. Ceiling grid in science labs are ongoing. Science casework is being installed, as well as light fixtures.
- Science lab casework install is ongoing on all three levels in the academic building.
- Auditorium cloud ceiling installation is progressing.
- Installation on grandstand bleachers is ongoing. Metal panel cladding is 90% complete. Pressboxglazing is 50% complete. Tennis courts fencing is complete. Stone masonry veneer on the retaining walls is ongoing.
October 23, 2023 Update
- Upper level windows in progress
- Corridor tile ongoing
- Ceiling grid installation in classroom areas B and C
- Glass installed in sky bridge and auditorium entrance
- Ceilings installed in cafeteria
- Girders installed in competition gym
- Auxiliary soccer field stands installed
September 25, 2023 Update
- Entrance to the auditorium vestibule is receiving spray foam insulation. Duct work and electrical are being installed in ceiling.
- Interior stone and wall tile installation is complete at the Bistro. Quarry tile flooring is also complete and covered for protection.
- Window frames have been installed at the bridge and glass is being installed.
- Wall tile at the main kitchen is complete. Duct work and overhead electrical are being installed.
August 28, 2023 Update
- Masonry and glass installation continue at the front of the main building.
- Work continues on the playing surface, restrooms, concession stands, and press box of the football field.
- Work continues on the water line and preparation for the temporary asphalt road.
July 24, 2023 Update
- Masons continue to lay brick on the front side and glass installation continues on the back side of the academic building.
- Structural work continues on the press box and field house. Light poles have been installed. Work on the home and visitor side concession stand and restrooms CMU continues.
- The pours for the tennis court slabs have begun. Minor competition field base is being leveled so that the e-layer can be poured.
June 12, 2023 Update
- Exterior work continues on the southern portion of the main academic wing with installation of siding. CMU block installation continues on the western side next to the lecture hall.
- The connector bridge floor has been poured, connecting academic area to the cafeteria, PAC, and athletics area.
- Framing and rough-in plumbing are progressing in the kitchen and cafeteria.
- Scaffolding in the PAC interior and fly loft is being prepared to begin work on the above ceiling.
May 22, 2023 Update
- Work continues on the main academic building.
- The connecting bridge from the academics to the cafeteria area continues with structural steel installation.
- Structural work continues on the home and visitor bleachers and press box. CMU block is being installed in the fieldhouse and is finishing in the multi-purpose center.
- Structural columns and home bleacher concrete continues in the competition gym.
April 24, 2023 Update
- Main entrance and front of the academic building are progressing with the installation of glass. The roof installation is still in progress.
- Work on the main gym continues. Installation of the frames for the windows has been installed. ICF pours will continue to complete the gym wall structure. the clay layer in the pond has been completed.
- Work continues on the stadium and field house. Slabs have been poured on the visitors' side along with laying CMU block for storage and restrooms.
- Hellas has mobilized to begin prepping the playing surfaces. Retaining walls are being poured in the tennis area. Retaining wall on the auxiliary field has been completed.
March 27, 2023 Update
- Retaining walls continue to progress in multiple areas around the site.
- Work is progressing on the kitchen and cafeteria areas.
- Work continues on the exterior of the main academic building.
- Interior metal studs continue to be installed along with rough-in mechanical and roofing on the main academic building.
- Vertical work begins in the main gym area.
- Concrete beams continue to be poured to support the seating for the home and visitor stands.
- The roof has been completed in the multi-purpose building. CMU block has begun on the walls.
February 27, 2023 Update
- Metal studs, rough-in electrical, and duct work are progressing in the lower and main levels.
- CMU block is in progress on the cafeteria.
- Progress continues on the storm shelter and gymnasium areas.
- Retaining walls to the eastern entrance to the visitor parking are near completion.
January 23, 2023 Update
- Iron work continues in the library area next to the courtyard. The library will have an abundance of natural light highlighted by the courtyard.
- Exterior framing of the administration area has been completed. “V” shaped columns mark the main level student entry.
- Steel columns and beams continue to be installed at the majority of the main academic wing of the building. Workers can be seen in the large lecture hall.
- CMU block continues to be installed at the auditorium. Notches in the block can be seen in preparation to receive structural steel beams.
- Formation of the press box has taken place as the main structural columns have been erected. Steel will continue as the concrete foundation finishes. Drilling of the piers for the athletic lights is underway.
December 12, 2022 Update
- Progress on the Performing Arts Center CMU block continues. Main academic area steel structure continues to expand to the west.
- Stadium visitor’s side grade beams have been completed. Home side is in progress with grade beams for the press box and stands. Baseball/softball complex final grading continues.
- Walls and sheet rock have started in the administration office area.
November 14, 2022 Update
- Main academic area steel is in progress.
- Paving continues on the west entrance that connects to the south entrance is in progress.
- Work continues on the home side of the stadium. Grade beam structure is ready for pour.
October 24, 2022 Update
- Work continues on the main academic building and fine arts area.
- Drilling of GEO wells continues. Work continues on ICF walls and slab pours.
- Stadium work is progressing on the home, visitor, and field house.
- Slab pours for the parking area around the field house is ongoing.
September 19, 2022 Update
- Work continues on the main building.
- Geo well drilling continues on the north side of the property. The first load of steel has arrived on site.
- Pier work continues on visitor’s side of the stadium. Finish grade work continues on home side.
- CMU block and ICF work progresses in the choir, band hall, and food labs. Slab pour finish work is in progress in the gymnastics area.
August 22, 2022 Update
Work continues on grade beams and slab prep in all areas of the main building. The slab is poured in a portion of fine arts. Laying of CMU blocks has begun.
May 2022 Update
Building pad for the cafeteria, fine arts, and gymnasiums is complete. Pier construction is ongoing.
April 2022 Update
Excavation work has begun in all areas of the site. Building pad preparation and moisture conditioning have started in the gymnasium area.
March 2021 Update
- VLK Architects presented to the board at the March 29 meeting. There are 10 steps that need to be completed before construction can begin. Below is a list with approximate date of completion:
- Drainage study – March 8
- Water and sanitary sewer study – March 29
- Preliminary plat – April 28
- Traffic circulation study – June 28
- Public improvement plans – June 29
- Community facilities agreement – July 23
- Construction of public improvements - August 27
- Final plat – August 30
- Addressing GIS – September 6
- Building permit – September 7
February 2021 Update
- Design and site development continues. VLK will present the prototype next month.
December 2020 Update
- Design and site development continues.
November 2020 Update
- Design and site development continues. Started design development with the architect team and departmental areas for input and reaffirming of needs.
October 2020 Update
- The design and site development continues.
- Design development started with the artchitect team and departamental areas for input and reafirrming of needs.
August/September 2020 Update
- Design and site development continues. Talks are in progress with developer regarding a middle school site.
July 2020 Update
- Design and site development continues
May 2020 Update
- Continue to have meetings with VLK and Civil Engineers. Preliminary Development Review Committee with City of Fort Worth for site and city concerns, recommendations, and requirements.
April 2020 Update
- Continue to have meetings with VLK. A virtual meeting was conducted with current high school and middle school students to gather information on things they liked in their schools, how they preferred to learn, and what would help them learn better in the future.

- August 24, 2026
- July 22, 2024
- June 17, 2024
- April 28, 2024
- April 22, 2024
- March 25, 2024
- February 26, 2024
- January 22, 2024
- December 11, 2023
- November 17, 2023
- October 23, 2023
- September 25, 2023
- August 28, 2023
- July 24, 2023
- June 12, 2023
- May 22, 2023
- April 24, 2023
- March 27, 2023
- February 2023
- January 23, 2022
- December 12, 2022
- November 14, 2022
- October 24, 2022
- September 19, 2022
- August 2022
- May 2022
- April 2022
- May 2020 Construction Photos
August 24, 2026
July 22, 2024
June 17, 2024
April 28, 2024
April 22, 2024
March 25, 2024
February 26, 2024
January 22, 2024
December 11, 2023
November 17, 2023
October 23, 2023
September 25, 2023
August 28, 2023
July 24, 2023
June 12, 2023
May 22, 2023
April 24, 2023
March 27, 2023
February 2023
January 23, 2022
December 12, 2022
November 14, 2022
October 24, 2022
September 19, 2022
August 2022
May 2022
April 2022
May 2020 Construction Photos
Liz Hatley Elementary School
Opened: August 2023
Mascot: Falcons
Colors: Purple and Gray
July 24, 2023 Update
-
Landscaping continues around all areas of the site. The office area is undergoing final punch list corrections. Main foyer flooring is complete with wall tile receiving grouting.
- Kitchen and serving lines have been completed and final cleaning and are ready for kitchen staff. Stage area is receiving punch item completion.
- Gymnasium school logo painting is near completion. Outside basketball court and sidewalks have been completed.
-
Hatley Move Timeline
-
7/13 –LCO (Limited Certificate of Occupancy) to begin delivery and assembly of furniture in the cafeteria, administration, and library areas.
-
7/18 –Delivery of custodial supplies and set up of trash cans.
-
7/24 –LCO (Limited Certificate of Occupancy) second floor furniture delivery.
-
7/25 –TCO (Temporary Certificate of Occupancy) for staff.
-
7/26 –Tentative move in date for administration.
-
7/27 –Basic Book pallets will be delivered to the campus.
-
7/31 –Custodial staff will begin cleaning.
-
8/1 –Campus professional development day. A detailed map for parking and entry will be created for the event.
-
8/4 –Custodians will begin waxing.
-
8/7 –Teachers will move into the building.
-
June 12, 2023 Update
- Installation of millwork in the admin area is almost complete.
- Ceiling tile and restroom floor tiles completed in areas A and B.
- Library ceiling grid has been installed and panels have been delivered.
- Ceiling grid and floor tile in cafeteria have been installed.
- Duct work and sheetrock installation continue in area D2.
- Connector walk way on the second floor is being prepped for glass installation. Basketball court and mow strip for playground have been poured.
- Brick layers continue installation in area D on the north and west walls.
May 22, 2023 Update
- Brick work is complete in academic wing C and is progressing in academic area D.
- Driveway approaches around the site are being poured.
- Administrative area continues with the installation of doors and library glass.
- Tile work is completed in the administrative area and continues in the hallway between the gymnasium and cafeteria. Lighting fixtures have been installed in areas A and B.
- Flooring protection is in place in the kitchen as equipment has been installed.
- These photos show the different progression from the top and bottom levels in area C and D.
April 24, 2023 Update
- Landscaping continues on the west and south side of the campus.
- Brick and rock installation are progressing on the administration and library areas.
- Sheetrock, tape and bedding and painting continue in the administrative area.
- Brick work is near completion in the gym area. Installation of an electrical transformer has been completed.
March 27, 2023 Update
- Main entrance and library continue with rough-in mechanical work. The roof on the library has been completed.
- Brick on the exterior of the gymnasium has begun. CMU block is complete in the gym and mezzanine areas.
- Storefront frames have been installed in the cafeteria. Landscaping, trenching and main lines are being installed.
- Sheetrock has started in the office area. Interior metal studs are progressing in the academic areas.
- Work continues on the mezzanine platform on the two academic wings.
February 27, 2023 Update
- Work continues on the main hallway and library. Installation of metal studs and HVAC duct work is in progress.
- Work continues on the second floor decking.
- Both bottom photos are of the cafeteria, focusing on the ceiling and stage construction.
November 14, 2022 Update
- Work on the ICF in the cafeteria continues. A grease trap has been installed.
- Piers and storm water continue to progress.
October 24, 2022 Update
- Storm water and GEO wells are in progress.
- Rough-in plumbing continues in the kitchen in preparation for the slab pour.
September 19, 2022 Update
- Overview of the site showing the main gymnasium and cafeteria areas.
- Steel installation for the grade beams is in progress.
Marine Creek Middle School
OPENed: August 2019
Mascot:Mustangs
Colors:Salty Dog Blue and White
ADDRESS: 5825 Marine Creek Parkway
Forth Worth, TX 76179
In a presentation to the Board of Education on July 22, 2019, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on May 20, 2019, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on March 25, 2019, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on February 25, 2019, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on January 22, 2019, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on December 17, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on November 5, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on October 15, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on September 18, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on August 27, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on July 23, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site
In a presentation to the Board of Education on June 18, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on May 21, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on April 16, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on March 26, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on February 19, 2018, Chief Operations Officer Clete Welch gave an update on the progress at the site.
In a presentation to the Board of Education on January 16, 2018, Chief Operations Officer Clete Welch provided an update on the project. Pier work is underway, plumbers are mobilizing, materials are on site, and manholes are being poured.
In a presentation to the Board of Education on December 11, 2017, Chief Operations Officer Clete Welch provided an overview of the work that has taken place. The project is making good progress and is on schedule for the school to open in August 2019.
In a presentation to the Board of Education on November 14, 2017, Chief Operations Officer Clete Welch explained to the Board that crews have begun work to prepare the site. The project is making good progress and is on schedule for the school to open in August 2019.
- July 2019 Construction Photos
- May 2019 Construction Photos
- March 2019 Construction Photos
- February 2019 Construction Photos
- January 2019 Construction Photos
- December 2018 Construction Photos
- November 2018 Construction Photos
- October 2018 Construction Photos
- September 2018 Construction Photos
- August 2018 Construction Photos
- June/July 2018 Construction Photos
- April/May 2018 Construction Photos
- November/December 2017 Construction Photos
July 2019 Construction Photos
May 2019 Construction Photos
March 2019 Construction Photos
February 2019 Construction Photos
January 2019 Construction Photos
December 2018 Construction Photos
November 2018 Construction Photos
October 2018 Construction Photos
September 2018 Construction Photos
August 2018 Construction Photos
June/July 2018 Construction Photos
April/May 2018 Construction Photos
November/December 2017 Construction Photos
Copper Creek Elementary School
The District closed on the property for Copper Creek Elementary School on February 13, 2018.
Projected Opening: August 2020
Mascot: Cowboys
Colors: Cardinal & Old Gold
August 2020 Update:
- Temporary Certificate of Occupancy has been received for staff and students
July 2020 Update:
- Staff waxing floors
June 2020 Update:
- Building signage is installed.
- Hat channel being installed to receive acoustical panel.
- Concrete is being prepped for flooring.
- Classrooms are locked and ready for furniture.
- Playground area is being landscaped.
May 2020 Update:
- Main lobby is being completed and finishes are being installed.
- Ceiling clouds are being installed.
- A masonry wall within the tornado scruture is installed. Duct work and lighting are also being installed.
- Gym masonry is progressing.
- Sidewalks are being installed between the academic wings.
- They playground system is installed.
April 2020 Update
- The cafeteria serving line is finished.
- The library cerculation desk area is finished.
- Classroom hallways are painted.
- Finished classrooms are carpeted and include cabinets and sinks.
March 2020 Update:
- Installation of tornado shelter
- Front view of school showing the new gym
- Library
- Main hallway entrance
- West view with main student pick-up area
- Sidewalk preparation for playground structure
February 2020 Update:
- Front view of main opening
- Progress of brick and stone
- Administrative area
- Library, ceiling grid, and paint
- Computer lab
- Cafeteria tiling
- Academic areas
- Academic classrooms
January 2020 Update:
- Aerial view overlooking the cafeteria
- Academic area brick work
- Finishing up steel frame
- Installing windows on 2nd level
- Wall framing in administrative area
- Academic area 2 sheet rock complete in hallway
- Wall framing on 2nd floor
- Wainscoting complete in hallway between cafeteria and gym
- Library windows installed
- Kitchen wall tile complete. Work continues on the flooring
- Bus canopy columns installed
- Gym walls have been delayed
December 2019 Update:
- Site work continues.
- The walls for the gymnasium/storm shelter are being constructed off site.
- Ceiling work, tiling, tape and bedding and painting is in progress in the kitchen and serving line.
- Kitchen equipment is being installed.
- Framing and sheetrock work is occurring in the library.
November 2019 Update:
- Masonry and windows near completion in the cafeteria area.
- Scaffolding is on site to brick the building.
- Masonry, windows and decking are underway in the academic wing.
- Prepping for window installation is underway in a couple of areas.
August 2019 Update:
- All the approaches have been poured.
- The cafeteria and kitchen with ICF forms in place.
- Classroom wings have the beginning of placement of ICF forms.
- Beams have been poured in the hallway between the kitchen and gym.
- Area between the blue fence and the road is the developers land that is dedicated for park land. The greenbelt area also has a walk/biking path.
July 2019 Update:
- Structural slab in cafeteria ready to pour.
- Grading process starting in Area 1.
- ICF blocking on-site and will begin going vertical in the cafeteria.
- Waiting on rebar in Area 2.
- North entrance being poured.
May 2019 Update:
- Contractors are working to minimize traffic through the neighborhood’s amenity center area.
- Pier drilling, utility installation and geothermal drilling is underway.
February 2019 Update:
- Pogue Construction was named as the general contractor for the project. TNP is working with the developer for electrical services and the notice to proceed is March 1, 2019.

- August 2020 Construction Photos
- July 2020 Construction Photos
- June 2020 Construction Photos
- May 2020 Construction Photos
- April 2020 Construction Photos
- March 2020 Construction Photos
- February 2020 Construction Photos
- January 2020 Construction Photos
- December 2019 Construction Photos
- November 2017 Construction Photos
- October 2019 Construction Photos
- September 2019 Construction Photos
- August 2019 Construction Photos
- July 2019 Construction Photos
- May 2019 Construction Photos
- March 2019 Construction Photos
August 2020 Construction Photos
July 2020 Construction Photos
June 2020 Construction Photos
May 2020 Construction Photos
Pictured above from left, ceiling clouds are being installed. Duct work and lighting are being installed in the tornado structure.
Pictured above from left, work is progressing at Copper Creek Elementary School and will open on time in August 2020. Masonry on the gym walls are progressing.
Pictured above from left, the playground structure is installed. Sidewalks are progressing between the academic wings.
April 2020 Construction Photos
March 2020 Construction Photos
February 2020 Construction Photos
January 2020 Construction Photos
December 2019 Construction Photos
November 2017 Construction Photos
October 2019 Construction Photos
September 2019 Construction Photos
August 2019 Construction Photos
July 2019 Construction Photos
May 2019 Construction Photos
March 2019 Construction Photos
Bryson Elementary School
Renovations are underway at Bryson Elementary School.
August 2019 Update:
- New front stone and brick entrance.
- New stone in the back of the gym.
- Finishing touches are underway in the gym.
- New tile and serving line with new cafeteria tables. New flooring is being installed on the hallway leading into the gym.
- New fencing and well house structure.
- New dumpster enclosure.
- New outside basketball court and playground with covers.
July 2019 Update:
- New moisture barrier installed on exterior and areas prepped for stone.
- Tile installed in the new kitchen serving line.
- New hallway added to gym entrance.
- Tiling is underway in the gym and iron work is being installed.
May 2019 Update:
-
West side of gym wall has been demolished.
- Well house has been demolished.
Highland MS, Creekview MS & Gililland ES
Renovations are underway at Highland Middle School, Creekview Middle School and Gililland Elementary School.
August 2019 Update:
- Landscaping at Creekview MS is in place.
- Landscaping at Highland MS is being installed.
- The media center, secure vestibule, and new kitchen serving line for students has been completed at Creekview.
- New surfacing of tennis courts and new wind slats has been added at Creekview.
- Tennis court slat installation is complete at Highland.
- Laying of new tile in hallway and media center at Highland.
July 2019 Update:
- Library ceiling grid, lighting, sheetrock, tape and bedding complete.
- Creekview and Highland: Storefront office glass, wall tiling, and wood slats installed in the library collaboration area.
- Creekview and Highland: Gyms have new LED lighting.
- Creekview: new floor tile in place, floors are waxed, new carpet in classrooms, gym floors are sanded.
- Highland: new irrigation system is being installed and wind slats at the tennis courts.
- Gililland: secure door added in the reception area.
May 2019 Update at Creekview & Highland:
- Doorframes have been installed and painted.
- Temporary wall has been added to a separate office area from construction inside the school.
- Ceiling tiles and lighting is complete.
- Finish painting is near completion.
- The aluminum storefront is being installed.
- Finish flooring and protective covering have been installed.
March 2019 Update:
-
Finalizing plumbing
February 2019 Update:
- Demolition of existing space is complete.
- Drywall is near completion.
Construction Photos
- March 2020 Construction Photos
- September 2019 Construction Photos
- August 2019 Construction Photos
- July 2019 Construction Photos
- May 2019 Construction Photos
- March 2019 Construction Photos
March 2020 Construction Photos
September 2019 Construction Photos
August 2019 Construction Photos
July 2019 Construction Photos
May 2019 Construction Photos
March 2019 Construction Photos
Lake Country Elementary School
Projected Opening: August 2021
Mascot: Lion
Colors: Gold and Black
August 2021 Update:
- The campus was ready for the first day of school on August 16, 2021.
July 2021 Update:
- Landscaping continues to progress, as does the rock and brick clean-up.
- Furniture is on site, being delivered, and assembled as needed.
- Gym floor has been installed along with the technology network.
- Playground area has been completed and is ready for school to begin.
June 2021 Update:
- Kitchen is ready for final cleaning
- Office area is 95% complete
- Upstairs classrooms ceiling grid have been installed
- Final above ceiling inspection needed before panels can be dropped in place
- The main corridor is complete except for flooring and sound panels
- Gym basketball goals are being installed
- Second grade hallway is being prepped for VCT
- 80% of the classrooms have carpet installed
- Rain caused delay in poring sidewalks which must be completed before playground installation can begin
April 2021 Update:
- Roofing and rock work continue to progress throughout the exterior of the building.
- Interior framing in the main hallway has been completed.
- Tile on the stage is complete and installation will begin this week in the main foyer.
- Drop-down ceiling in the library has been completed.
- Framing and HVAC continue on the second level.
- Millwork in the music/art room has been installed. CMU block in the gym is completed. A primer paint has been applied and waiting for final coat of paint.
- Metal roof panels have arrived on site waiting for installation. Spring Street entrance has been poured connecting with the bus loop.
March 2021 Update:
- Irrigation installation for the detention pond is in progress.
- The driveway entrance is being prepped.
- The parent drop-off on the north side of the building has been poured and tied in to the main entrance.
- Stone and brick are being installed in the front of the building.
- Wall tile has been installed in the gym/cafeteria hallway.
- Wall tile, ceiling grid, and quarry tile have been completed in the kitchen area.
- The gym floor and rough-in plumbing have been completed.
- Cabinetry in the library has been installed along with delivery of the wooden doors.
February 2021 Update:
- Front entrance main roof structure has been installed. Tornado shelter panels and roof are being installed.
- Main front drive with sidewalk that connects the north and south ends of the property has been poured.
- Parent pick-up loop forms and rebar are being set for concrete pour. Detention concrete work is complete.
- Kitchen hood is 90% complete.
- Geo well trucks working on setting pipe loops.
- Cafeteria ceiling tile grids have been installed waiting for drop-in tiles.
- Freezer and cooler have been installed in the kitchen.
- First floor academic wing door frames, metal studs, and rough-in electrical are in progress.
- First and second grade installation of hallway columns are in progress.
- Shelving, lighting, and very large fan is being installed.
- Photos of the new warehouse office located by the dock to receive district supplies.
December 2020 Update:
- Lift is being used to lift the joist to be installed in the cafeteria.
- East drive is being poured.
- Pump truck being utilized to assist in concrete pour on eastern edge of the property.
- Form boards have been staked in place and rebar is tied together for concrete pour.
- Retaining wall for detention pond is in the process of being formed up for concrete.
- Retaining wall is 90 percent complete.
- Decking has been installed above the joist in the cafeteria.
- Elevator walls are 90 percent complete.
- IFC walls are being installed in kindergarten and first grade hallway.
- CMU blocks are being installed in the kitchen area.
- Welder is installing beams between the cafeteria and gym.
- CMU block is being installed in the freezer area of the kitchen.
November 2020 Update:
- Construction continues on the campus. A concrete retaining wall to support the detention pond has been installed.
- Oncor is in the process of install ing permanent power.
- Site prep is in progress for the kitchen approach and drive.
- the academic and library slabs have been poured.
- The IFC is prepped for a concrete pour.
- the CMU block is being installed in the computer lab and hallway restroom.
- Modular block installation is occuring in the back side of the property.
October 2020 Update:
- Box cartons will be used to support slab during the pour
- Cardboard sheathing will also be used to enhance stability of the surface during the process.
- Iron Busters team have tied rebar together to prep for pour.
- Kitchen vertical ICF (issued for construction) was prepped for concrete pour.
- CMU (concrete masonry unit) block was laid between the art room and hallway.
- Concrete finishers completed work 10 hours after first truck of concrete.
- Dirt grading took place on Lake Country Drive and lime stabilization was in progress.
- Work is in progress on concrete and modular block retaining walls.
- The headend of a box culvert is finished.
September 2020 Update:
- Construction crews have installed a stormwater pipe and a grease trap.
- The beams are curing.
- The kitchen rough-in plumbing and fine grading are underway.
- Soil has been removed for the retaining wall and crews are drilling geo wells.
August 2020 Update:
- Working on the final cut on the southeast corner of the property.
- Three building pier machines are on site.
July 2020 Update:
- New southern entrance and tree protection being installed.
- Gradework has begin and run-off fencing has been installed.
June 2020 Update:
- Site visit to pin the building corners down. Reviewing final finishes

Construction Photos
- August 2021 Construction Photos
- July 2021 Construction Photos
- June 2021 Construction Photos
- April 2021 Construction Photos
- March 2021 Construction Photos
- February 2021 Construction Photos
- November 2020 Construction Photos
- October 2020 Construction Photos
- September 2020 Construction Photos
- August/July 2020 Construction Photos
- June 2020 Construction Photos
August 2021 Construction Photos
July 2021 Construction Photos
June 2021 Construction Photos
April 2021 Construction Photos
March 2021 Construction Photos
February 2021 Construction Photos
November 2020 Construction Photos
October 2020 Construction Photos
September 2020 Construction Photos
August/July 2020 Construction Photos
June 2020 Construction Photos
Boswell High School
Multiple renovations have been made at Boswell High School. The agriculture science building, roughly 6,600 square-feet, includes two classrooms, a shop for welding and woodworking, staff offices, and restrooms. Additionally, the old turfroom at BHS was renovated to accommodate this season’s sports. This space was remodeled to include coaching offices, a locker room, and trainers’ room. These spaces were previously located in the main campus. The weight room was upgraded, too.
January 24, 2022 Update:
- Netting installation and punch items continue in the turf room.
- Visitor ticket booth is near completion.
December 2021 Update:
-
Netting installation, dividers, ceiling protection, and batting cages in progress.
-
Area C is dried in, and stone installation on south end of building is in progress.
November 2021 Update:
- The turf room interior logo has been installed in the new stadium. The north wall construction still continues. Landscaping continues to be planted.
September 2021 Update:
- The landscape is in progress. Grandstands still need brick wall and numerous glass panels.
- Older handrails have been sand blasted, primed, and a gray finish applied to smooth out the railings. Fencing around grandstand continues to progress.
- The bus parking lot has been striped and is ready for buses. Work continues in the pressbox.
- Hellas has started the interior turf installation. The brick has been completed and cleaned on the turf room.
- Work continues on the monument sign.
August 2021 Update:
- Coaches parking area is receiving the final grade in preparation for concrete pour. Interior of the turf room roof construction is complete. Painting of the metal structure is in progress.
- Grandstand and pressbox is progressing to be completed before the first home game.
- Wood floors in the Newcom Gym and West Gym have been sanded and resurfaced.
- The make-over of the gymnastics area is complete.
- Weight room and offices have been furnished. Punch list items are ongoing.
July 2021 Update:
- Main grandstand structure is in progress.
- Workers continue to lay brick on the west, south, and north sides of the pressbox.
- Visitor’s bleachers main concourse retaining wall has been poured. Bleachers are scheduled to arrive on August 2. Construction, with good weather, should only take three weeks.
- Views from the pressbox show the main field and new weight room area.
- Pressbox construction continues with rough-in electrical, insulation, and sheetrock.
- Main walkway between the field and dressing rooms is progressing.
June 2021 Update:
- Stadium grandstand is scheduled for arrival on July 2, 2021
- Stadium masonry columns have been completed
- Concrete flatwork needs to be completed before granstand installation
- Metal studs are on backorder due to supply issues
- Light poles have arrived on site and visitor bleacher pier drilling has resumed; must be compelted by June 16, 2021
- CMU block work is near completion on the visitor's side ticket booth
- Wall tile work in shower rooms have been completed
- Interior renovation of the gymnastics area includes expanding the storage areas, public restrooms, new locker rooms and lockers, new offices, fire sprinkler installed, LED lighting and painting
April 2021 Update:
- Stadium
- CMU blocks have been completed for the press box and restrooms. Steel has been installed on levels 1, 2, and 3.
- Storage area concrete is in the process of being poured. A new concession stand, CMU block, and door jams are in place. Demolition of the visitor’s stands has begun.
- Structural framing on the turf room continues and will be completed within the next week.
- HVAC duct work is in the process of being installed in the weight room.
- Installation of the glass in the weight room started.
- This is last structural beam to be installed and was autographed by Boswell students.
- Roofing on the tennis pavilion has been completed.
March 2021 Update:
- Stadium
- Three towers of the CMU block are going vertical up to 50 feet.
- The main retaining wall and pier casings will support the structure on the home grandstands.
- Structural steel supports are being installed for the turf room and the weight room balcony.
February 2021 Update:
- Grandstand piers and retaining wall has been completed.
- Plumbing and electrical rough-in is in progress for the main pressbox.
- New turf room slab and CMU block work is in progress.
- Steel supports for office space and second floor conference room are in progress.
- Steel structure for main student entrance has been welded in place.
- Second floor joist and decking are being installed.
- CMU walls, rough-in plumbing, and duct work are 70% complete in the Varsity and JV locker rooms and shower area.
- Photos show new main football corridor with trophy cases.
- Gymnastics new locker room space and additional storage is progressing.
- CMU walls and second floor beams have been installed in the office area.
- The joists and beams are being installed, along with door jams, in the second story above the main hallway.
- Training room joist have been installed and CMU blocks for the office. Joist and decking are being installed in the freshman locker rooms.
January 2021 Update:
- Area C slab is completed. Area C consists of the training room, freshman football lockers, coaches’ offices, and dressing areas.
- Turf room grade beams construction is near completion. The grade beams support the steel for the pre-engineered metal building.
- Installation of the plumbing and showers in the varsity locker room is progressing.
- New CMU corridor wall between the gymnastics gym and varsity locker rooms is under construction.
- Overview of the construction site from the visitor’s stands.
December 2020 Update:
- Press box pad is being prepped.
- Dirt work between the turf room and offices are being graded.
- Plumbing is being installed for the freshman locker room.
- Walkway has been poured from the main building to the new athletic facility.
- Slab for the varsity and JVlocker room has been poured. CMU block has been delivered for wall construction.
- Slab preparations for the gymnastics offices and dressing rooms.
- Additional shortage and restroom for gymnastics area. The first row of CMU block has been laid.
- Turf room grade beam is being formed up. This is located next to the Max Newcom Gym.
November 2020 Update:
- Stadium demolition is in progress.
- Grade beams for the coaches' office and dressing rooms are being is installed.
- Slab preparations are being made for the gymnastics dressing rooms.
- Additional storage and restrooms for gymnastics area is being isntalled. The vertical wall will have cutouts to access new areas.
- New handicap ramp is being installed by the Dennis Dance and Cheer Building.
October 2020 Update:
- The first section of grade beams have been poured. The first lab pour at the gymnastics addition is scheduled for November 23.
- the grade beams for the locker room area are under construction.
September 2020 Update:
- Lanscaping is complete at the Kenneth K. Reed Agriculture Science Building.
- Drilling piers are installed at Pioneer Stadium.
August 2020 Update:
- Paving on the parking lot is ahead of schedule, striping has been completed
- Continue working on the underground utilities on main addition
- Pouring the sidewalk and installing a canopy
- Final finishes on the agriculture building, completing the agricultural punch list.
- Coaches have moved into the athletics facility. Contractors are working on the final punch items.
July 2020 Update:
- The entrance to the stadium has been expanded
- Lime stabilization of the parking lot took place
- Utility work is taking place
- Masonry is in progress at the Ag Science building
- Restroom tile work, office and classroom updates and lab finalization is taking place at the Ag Science Building.
- The locker bases and celing tiles have been installed at the athletics building.
- The old turf area with new training room, and remaining space will be organized into a weight room at the athletics building.
June 2020 Update:
- Utilities are being completed, the entrance is being expanded, and the old baseball fence has been removed.
- The Ag Science building masonry is in progress as well as framing and ductwork.
- Turf building rennovations are underway, and plumbing lines have been installed.
- Demolition is in progress and new electrical building and pathway are complete.
- There has been a parking lot, stormwater and asphalt removal.
May 2020 Update:
- Ag Science building concrete masonry blocks are progressing.
- New mechanical building progressing.
April 2020 Update:
- New electrical routing is complete.
- Slab is poured for the new tennis court.
August 2019 Update:
- Aerial view of Kenneth K. Reed Agriculture-Science Building
August 2019 Update:
- Marching field is complete for Boswell band.
- The final layer of crushed stone is being added in preparation for the turf installation at the baseball and softball fields. We anticipate completing these projects by mid September.
July 2019 Update:
- Band parking lot is being prepped.
- Turf E-layer is complete on main stadium.
- Completing E-layer on auxiliary field.
- Moisture conditioning has resumed on softball and baseball fields.
May 2019 Update:
- Work on the band parking lot is underway.
- Work is beginning on the baseball field.
- GEO fill has been delivered.
Construction Photos
- January 2022 Construction Photos
- December 2021 Construction Photos
- November 2021 Construction Photos
- September 2021 Construction Photos
- August 2021 Construction Photos
- July 2021 Construction Photos
- June 2021 Construction Photos
- April 2021 Construction Photos
- March 2021 Construction Photos
- February 2021 Construction Photos
- November 2020 Construction Photos
- October 2020 Construction Photos
- September 2020 Construction Photos
- July 2020 Construction Photos
- May 2020 Construction Photos
- April 2020 Construction Photos
- March 2020 Construction Photos
- February 2020 Construction Photos
- October 2019 Construction Photos
- September 2019 Construction Photos
- August 2019 Construction Photos
- July 2019 Construction Photos
- May 2019 Construction Photos
January 2022 Construction Photos
December 2021 Construction Photos
November 2021 Construction Photos
September 2021 Construction Photos
Pictured above left is the memorial sign for the BHS baseball complex. Pictured above middle is the fencing surrounding the stadium grandstand. Pictrued above left is the stadium handrails.
Pictured above left, progress continues on the turf room. Pictured above middle, the turf for the turf room will soon be laid. Pictured above right, the landscaping at the stadium is nearing completion.
Pictured above left, the lparking ines have been drawn for buses. Pictured above, construction continues for the pressbox. Pictured above right, construction workers continue work inside the pressbox.
August 2021 Construction Photos
Pictured above left is the BHS gymnastics area. Updates are completed. Pictured above middle is the coaches' parking area. Pictured above right is the Newcom gym. Wood floors have been resurfaced.
Pictured above left is the coaches' office area. Updates are completed. Pictured above middle is the stadium. Press box construction is underway. Pictured above right is the tennis court contruction progress.
Pictured above left is the construction progress of the turf room. Pictured above right is the completed weight room.
July 2021 Construction Photos
Pictured above from left are a view of the athletics building and the visitor’s bleachers main concourse retaining wall.
Pictured above from left are a view of the football field and visitor's bleachers.
Pictured above from left are the pressbox and main walkway between the field and dressing rooms.
Pictured above is the pressbox.
June 2021 Construction Photos
April 2021 Construction Photos
March 2021 Construction Photos
February 2021 Construction Photos
November 2020 Construction Photos
October 2020 Construction Photos
September 2020 Construction Photos
July 2020 Construction Photos
Top row: Masonry is being completed on the agriculture building. Next, a classroom is in the process of being completed. Second row: Ag building lab is being finalized. The ag building office is being completed. Bottom row: Bathroom tile is being installed in the Ag buildin. Utilities are being worked on.
May 2020 Construction Photos
April 2020 Construction Photos
March 2020 Construction Photos
February 2020 Construction Photos
October 2019 Construction Photos
September 2019 Construction Photos
August 2019 Construction Photos
July 2019 Construction Photos
May 2019 Construction Photos
Jim F. Chadwell Administration Building
October 24, 2022 Update
- Staff is getting settled in their new spaces in the new administration office.
September 19, 2022 Update
- Work continues onpunch items in Area C –employee entrance.
- Finishing touches on furniture and installation of monitors in Area B.
- Installation of mill work and finish items in the board room area continues.
August 22, 2022 Update
- The dais area is undergoing final installation and staining of wood panels.
- Finish items and punch items are progressing in Area C.
- Finishing touches on the reception desk continues along with furniture delivery and install in Area B training room.
- Work continues in the new offices.
July 25, 2022 Update
- Admin landscaping continues to progress.
- Furniture has been installed in Area C and punch items are still progressing.
- Bistro equipment continues to be installed. Lighting and painting continue in Area A – Board Room.
- EMHS-three months progress on the eastern portion of the property focusing on the stadium complex.
- Elementary 18 - Building pad preparation has begun. Dirt work is in progress
June 20, 2022 Update
- Millwork continues in Area B on the main and upper level.
- Ceiling and sheetrock continue in board room.
- Carpet and lighting continue in Area B on the main and upper level.
- Bistro equipment continues to be installed, and punch items in Area A continue.
- Building pad preparation continues along with grade cuts.
- Turf projects are on schedule at Chisholm Trail HS and Saginaw HS. They are due for completion in July.
May 2022 Update
- Retaining wall and planting
- Lighting and ceiling in Area B
- Work stations and mailroom in Area B
April 2022 Update
- Progress on the exterior finishes continue on schedule.
- Exterior finishes continue and decking has begun on the balcony.
- Millwork, lighting, and stairway handrails are in progress.
- Ceiling finishes continue to progress in all areas of the building.
March 2022 Update
- New Administration building exterior wall panels installation is in progress.
- Installation of ceiling grids in all sections of the building is in progress.
- Bistro equipment installation is in progress. Technology cable wire is being pulled throughout the building.
- Rock wall work is nearing completion
- Chisholm Trail HS baseball retaining wall repair is in progress.
- Eagle Mountain High School:
- Core Construction has mobilized on the site.
- Construction entrances have been installed.
- Fencing has been installed for erosion control.
- Grading permit is in progress with the City of Fort Worth.
February 2022 Update
- Final landscape grade is in progress around the west and south sides of the building.
- Metal roof is near completion in Areas A, B, and C.
- Glass framing is being installed in Area C.
- Construction of the back walkway is in progress. Mechanical duct work is being installed in Area C.
- New fencing is complete around well fixtures at Eagle Mountain ES and Elkins ES.
January 2022 Update
- The deck is installed, foundation poured, and iron work for roof is ongoing in Area A.
- Glass frames and glass are being installed in the Absher area. Rock and sheetrock continue on the back of the building.
- Board room dais structure has been poured. Framing and sheetrock continue in the Ramsey area.
December 2021 Update
-
The deck is installed, foundation poured, and iron work for roof is ongoing in Area A.
-
Exterior sheathing, framing, roof installation, and fire sprinkler installation continues in Area B.
November 2021 Update
-
In Area B, the second-floor deck is being completed. The stairs have been installed to the second floor, and the iron work continues in this area.
-
In Area C, the exterior sheathing, rock work, interior wall framing, and rough-in electrical continues.
October 2021 Update
- Iron work continues. Exterior and interior framing in Area C is progressing. Mock up is 60% complete.
- Work continues on the installation of the pipe for the fire system, roof framing, and concrete blocks on the lower level.
September 2021 Update
- The steel structure installation over the Finance, Superintendent, and Operations suites is being installed.
August 2021 Update
- Concrete Masonry Unit walls continue to be built in lower level
- Exterior walls and grade beam construction continues on the north side of the building
July 2021 Update
- The CMU block is being utilized to form up the walls on the lower level. Rebar is in place to pour the main entrance to the building.
June 2021 Update
- The northern parking lot pour has been completed
- Site work delayed due to rain
- Eastern walls in the business area are being formed for future concrete pour
April 2021 Update
- Piers are in the process of being drilled. They are filled with rebar and concrete, and 180 of the 300-plus piers have been completed.
March 2021 Update
-
The parking lot is being excavated and soil relocated on site.
-
The building site is being excavated and prepped for piers.
February 2021 Update
- Construction trailer has been set in place with electricity and data. The security, silt, and tree fencing are complete.
December 2020 Update
- Naming the general contractor is an action item for Board consideration at the December meeting.
November 2020 Update
- Competitive sealed proposal has been released for bidding. Project will come to the Board for consideration in December for the naming of the general contractor. CSP is out for bid. A pre-construction meeting was held last week to answer questions about the project.
October 2020 Update
- The competitive Sealed proposal has been released for bidding. The project will come to the Board for consideration in December 2020 for the naming of the general contractor.
September 2020 Update
- Still in final review, competitive sealed proposal (CSP) will be recommended as the procurement method.
August 2020 Update
- Still in final review, competitive sealed proposal (CSP) will be recommended as the procurement method.
July 2020 Update
- Reviewing final finishes
June 2020 Update
- Site visit to pin the building corners down. Reviewing final finishes
May 2020 Update
- Continued design meetings. Projected construction will begin in Fall 2020.
April 2020 Update
- Continue design meetings. Projected construction will begin in Fall 2020.
- October 24, 2022
- September 19, 2022
- August 22, 2022
- July 25, 2022
- June 20, 2022
- May 23, 2022
- April 25, 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
- September 2021
- August 2021
- July 2021
- June 2021
- April 2021
- March 2021
- February 2021
October 24, 2022
September 19, 2022
August 22, 2022
July 25, 2022
June 20, 2022
May 23, 2022
April 25, 2022
March 2022
February 2022
January 2022
December 2021
November 2021
October 2021
September 2021
August 2021
July 2021
June 2021
April 2021
March 2021
February 2021

Wayside Middle School
This project is being completed in the 2023 Bond Projects
February 2021 Update
- VLK will present the site development this month.
December/November/October 2020 Update
- Site development is being worked on.
August/September 2020 Update
- Working on site development, meeting with the City of Saginaw for review of site plan.
July 2020 Update
- Working on site development
Maintenance Facility
March 2021 Update
- Substantial completion of the facility to be completed in April.
December 2020 Update
- New view of the building from the road.
- Warehouse exterior metal panels are being installed.
November 2020 Update
- The grade beams have been poured and the final grading for the slab pour is in progress.
October 2020 Update
- The framing and pouring of grade beams is in progress.
August/September 2020 Update
- The building site is prepped and moisture conditioning is complete.
July 2020 Update
- The generator pad with electrical tubing is in place within the server room.
- Additional HVAC support has been installed.
May/June 2020 Update
- Network Operations Center to be completed in August.
April 2020 Update
- Network Operations Center (NOC) – Design and ordering of materials in progress
Construction Photos
Safety and Security
All Safety and Security Updates pertaining to the 2017 Bond were completed in 2021
March 2021 Update
- Security Upgrades at Multiple Campuses and Jim Knight Maintenance Facility Additions and Renovations – Access control, storefront, and hardware have been completed at Bryson ES, Eagle Mountain ES, and Willow Creek ES, Wayside MS, Chisholm Trail HS, Saginaw HS, and Watson HS. Punch list and CO items will still be ongoing
December 2020 Update
- Security Upgrades at Multiple campuses and Jim Knight Maintenance facility Additions and Renovations - Prep work has been completed. Hardware will be delivered during the break. Install will also begin during the break.
November 2020 Update
- Security Upgrades at Multiple Campuses and Jim Knight Maintenance Facility Additions and Renovations – Work has progressed to 80% for all buildings in the project. Testing continues on access control and cameras.
September 2020 Update
- Security Upgrades at Multiple Campuses and Jim Knight Maintenance Facility Additions and Renovations – Work has begun on Bryson ES, Wayside MS, Hollenstein CTC, and Ed Willkie MS. Testing cable signal strength, cameras, hardware, and replacing damaged doors from previous security upgrade contractor.
August 2020 Update
- Security Upgrades at Multiple Campuses and Jim Knight Maintenance Facility Additions and Renovations – Contractor is ordering hardware, they are working on the permit and notice to proceed on the warehouse.
July 2020 Update
- Security Upgrades at Multiple Campuses and Jim Knight Maintenance Facility Additions and Renovations – GMP is under consideration tonight
June 2020 Update
- Construction Manager at Risk under consideration at June 2020 board meeting
May 2020 Update
- Maintenance Addition and Multiple Security Projects – Procurement method is being recommended as an action item for the May 2020 meeting. Design development complete. Construction documents to be completed late May. As a reminder, this is a consolidation and streamlining of warehouse services.
April 2020 Update
- Maintenance Addition and Multiple Security Projects – The district will continue to define the scope.